Moon mission could cost $50 billion, NASA says in report criticizing Boeing

NASA’s SLS moon rocket is 30 percent over budget, report says

NASA’s SLS moon rocket is 30 percent over budget, report says

In truth, your complete SLS program is over funds and not on time by greater than 33 %, in comparison with the baseline figures NASA gave Congress for 2019.

The Gateway will orbit near the Moon and will be occupied periodically by astronauts as part of NASA's sustainable lunar exploration plans.

WASHINGTON-Questionable contracting procedures, unnecessary accounting problems, schedule delays, and more than $2 billion in cost overruns are raising serious doubts about NASA's plan to return Americans to the Moon in late 2024, according to the agency's inspector general (IG).

ESA, the Japanese Aerospace Exploration Agency, and the Canadian Space Agency are all actively engaged in discussions with NASA to support the construction and operation of the Gateway which, again, will support lunar surface missions and pave the way for the human exploration of Mars.

What's more, these extensions and difficulties (some at NASA, some at contractors and subcontractors) have complicated finances and caused the program to blow past its original budget. The first core stage of the SLS had had its engines fitted and had been shipped for Green Run testing.

Major League Baseball suspends spring training, delays Opening Day
All members of the Jazz were tested for the virus, and another individual's results were positive, the team said in a statement. Major League Baseball will continue to undertake the precautions and best practices recommended by public health experts".

"NASA's continued struggle with managing SLS Program costs and schedule has the potential to impact the Agency's ambitious goals for the Artemis program". NASA has estimated that the expenditure on the SLS program until the end of 2020 will be $17 billion. Since the replan, the SLS Program now projects the Artemis I launch will be delayed to at least spring 2021 or later. Part of this is simply in how it's reported, but it also means that what has been accomplished has cost more than expected. "Every of the key factor contracts for creating and constructing the SLS for Artemis I-Levels, ICPS, Boosters, RS-25 Adaptation, and RS-25 Restart-have skilled quite a few technical challenges, efficiency points, and requirement modifications which have resulted in $2 billion of price overruns and will increase and at the very least 2 years of schedule delays". The blame for the issues is mostly placed on Boeing, the contractor of the project. This specific report additionally comes at a susceptible time for Boeing, just some months after the corporate's different spacecraft in growth, the CST-100 Starliner, made a less-than-stellar debut flight for NASA.

Northrop Grumman and Aerojet have also experienced issues, according to the report, with problems relating to the Booster's propellant liner and insulation, and a new Engine Controller Unit for the Shuttle era RS-25 engines proving hard to overcome. While NASA has addressed numerous problematic issues in Core Stage, ICPS, Booster, and RS-25 Engine development, we expect additional cost increases totaling approximately $1.4 billion-$1.3 billion for Stages, $107 million for Boosters, and $41 million for ICPS-before the Artemis I launch.

NASA has selected the first science instruments for the Gateway lunar outpost.

When NASA announced in 2019 the Artemis program to put us astronauts on the Moon's surface in late 2024, the plan was to use the Space Launch System (SLS), a two-stage heavy-lift rocket, to put the Orion Multipurpose Crew Vehicle (Orion) into space.

Full report Therefore, this recommendation is unresolved pending further discussions with the Agency.

Recommended News

We are pleased to provide this opportunity to share information, experiences and observations about what's in the news.
Some of the comments may be reprinted elsewhere in the site or in the newspaper.
Thank you for taking the time to offer your thoughts.